Stallaert Héliport construction site

Stallaert Héliport construction site


donderdag 2 maart 2017

For the Ex-Riverside construction site, situated at the crossing of the Avenue de l’Héliport and the Allée Verte in Brussels, Stallaert is moving about 35.000 m3 of earth.

The earth to be moved is of different qualities. One of the main difficulties in Brussels is the road traffic congestion. To be able to remove that amount of earth, a lorry would have to make 2100 trips. This is the reason why Stallaert chose to evacuate the earth by waterway. There will therefore only be 16 boats leaving the Port of Brussels. Transport between the site and the loading site only takes 3 minutes with tractors, as these adhere better to the instable surfaces.